Frequently Asked Questions

Answers to the most common questions about California construction law.

General Questions

Mechanics Liens

Contractor & License Issues

Payment & Collections

Construction Defects

Critical Deadlines

California Construction Law Deadline Quick-Reference

Missing a construction law deadline in California can permanently forfeit your rights. This table summarizes the most critical deadlines — but every case has unique facts that can affect the applicable period. Always confirm your specific deadline with qualified counsel.

Deadline / ActionTime LimitTrigger EventAuthorityWho It Applies To
Preliminary 20-Day Notice
20 daysFirst furnishing labor or materialsCivil Code §§ 8100–8118Subcontractors, suppliers, design professionals (not direct contractors)
Mechanics Lien — Record (no NOC)
90 daysCompletion of work / projectCivil Code § 8412All lien claimants
Mechanics Lien — Record (after NOC)
60 daysRecording of Notice of Completion or CessationCivil Code § 8414All lien claimants
Mechanics Lien Foreclosure Lawsuit
90 daysRecording of the mechanics lienCivil Code § 8460Lien claimant
Stop Payment Notice (Private Works)
Same as lien deadlineUnpaid after completion / NOCCivil Code §§ 8500–8560Subcontractors, suppliers (requires valid prelim notice)
Stop Payment Notice (Public Works)
30 days after NOCRecording of Notice of CompletionCivil Code §§ 9350–9364Subcontractors, suppliers on public projects
Payment Bond Claim (Public Works)
30 days after NOCRecording of Notice of CompletionCivil Code § 9558; Pub. Contract Code § 9202Subcontractors, suppliers on public projects
Breach of Written Contract
4 yearsDate of breachCCP § 337Any party to a written construction contract
Breach of Oral Contract
2 yearsDate of breachCCP § 339Any party to an oral construction contract
Construction Defect (Patent / Obvious)
4 yearsDiscovery of defectCCP § 337.1Property owner against contractor/designer
Construction Defect (Latent / Hidden)
3 years from discovery; 10-year reposeDiscovery; or substantial completion (repose)CCP §§ 337.15, 338Property owner against contractor/designer
SB 800 Right-to-Repair Notice (Residential)
Before filing lawsuitDiscovery of residential construction defectCivil Code §§ 895–945.5Homeowner against builder of new residential construction
Professional Negligence (Architect/Engineer)
3 years from discovery; 10-year reposeDiscovery of negligence / substantial completionCCP § 338; Bus. & Prof. Code § 5536.1Owner or contractor against design professional
Prompt Payment Penalty (Private)
2% per month on late paymentsPayment overdue (30 days owner→GC; 7 days GC→sub)Civil Code §§ 8800–8802GC against owner; subcontractor against GC
CSLB Complaint Filing
4 years from act / discoveryContractor violation or abandonmentBus. & Prof. Code § 7091Owner, subcontractor against licensed contractor
Contractor License Bond Claim
2 yearsDate of contractor's act causing damageBus. & Prof. Code § 7071.5Owner or subcontractor against contractor's bond
Red triangle = deadline that permanently forfeits rights if missed. This table is for general reference only — not legal advice.
Calculate My Specific Deadlines

Don't See Your Question?

Call us. We'll answer your specific question for free.

Start Your Case Review