Representative results from our construction litigation practice. Past results do not guarantee future outcomes.
General contractor completed a $12M commercial project. Owner refused to release final $4.2M, claiming nonexistent construction defects.
Filed mechanics lien within statutory deadline, initiated litigation, retained engineering expert who demolished the owner's defect claims in deposition.
Full $4.2M recovered plus attorney fees. Settled 8 months after filing.
General contractor on a $28M hospital renovation experienced 14 months of owner-caused delays. Owner blamed the contractor.
Retained delay expert who performed critical path analysis demonstrating 11 of 14 months were owner-caused. Pursued extended overhead and escalation claims.
$2.1M in delay damages recovered.
Specialty subcontractor terminated mid-project by GC who hired a cheaper replacement. Sub owed $1.8M for completed work.
Pursued GC and property owner through mechanics lien foreclosure and breach of contract simultaneously.
$1.8M recovered. GC's license complaint dismissed.
Partner in a $20M/year GC company was secretly diverting business opportunities to a new company.
Obtained emergency injunction stopping diversion. Pursued breach of fiduciary duty claims with full accounting.
$1.2M in diverted profits recovered plus attorney fees.
Developer faced $3.5M construction defect lawsuit claiming structural defects, water intrusion, and code violations.
Physics-trained attorney analyzed technical evidence and identified defects were caused by owner's own post-completion modifications.
Case dismissed. Developer paid $0.
Commercial property owner suffered $850K in damage when neighboring construction caused soil subsidence damaging the foundation.
Documented damage, retained geotechnical expert, pursued claims against developer and contractor.
$850K plus remediation costs recovered.
Subcontractor owed $680K by general contractor who became insolvent on a $45M public works project.
Identified payment bond, served timely notice on surety, filed bond claim within all deadlines.
Surety paid $680K within 90 days.
Material supplier delivered $420K of materials. GC refused to pay, claiming defective materials (they weren't).
Served stop notice on owner and construction lender, halting $420K in draws.
GC settled within 30 days to restore project financing.
General contractor improperly disqualified from $22M public works bid in favor of higher-priced competitor.
Filed bid protest within 5-day deadline, documented agency's failure to follow its own evaluation criteria.
Court ordered re-evaluation. Client awarded the contract.
Subcontractor performed $380K of extra work based on verbal directions. GC refused to pay citing written change order requirement.
Documented verbal directives through emails, texts, and witnesses. Pursued quantum meruit claim.
$340K recovered — 89% of claimed amount.
Property owner paid $280K to contractor who completed only $40K of work and abandoned the project. Contractor filed false lien waivers.
Pursued civil fraud claims, obtained judgment for $280K plus punitive damages, coordinated with law enforcement.
Full judgment plus punitive damages. Contractor's license revoked.
General contractor received CSLB complaint alleging project abandonment. Complainant sought $180K in restitution.
Investigated facts, documented owner's failure to make required payments that caused work stoppage.
Complaint dismissed. No restitution. License intact.
GLG has represented California contractors, developers, and property owners in high-stakes construction disputes. Start your case review today.